Closure extended for New Circle Road in Fayette Co.
LEXINGTON, Ky. (WTVQ) – The Kentucky Transportation Cabinet advises motorists that this advisory serves as an update for work toward the New Circle Road/KY 4 widening project in Lexington.
KYTC says the ramp will not reopen at 7 p.m. Tuesday night, as originally scheduled. It will open Wednesday, April 17, at noon.
You can use the alternate route signed on Georgetown Road to Citation Boulevard for access to I-75 and I-64
The construction includes Georgetown Road/US 25 to Boardwalk Avenue. In addition, the interchange is being reconstructed at Newtown Pike/KY 922. The anticipated completion date for the project is December 31, 2020.
All work is scheduled on a tentative basis and is subject to change depending on weather conditions, emergencies and other factors beyond the control of the Department of Highways.